Better late than never

Revised dates for replacement of the canal steps at University station have been published. Unfortunately a 6-week delay in starting means there will be still be disruption in term-time:

  • Overall construction phase 08.08.16 to 17.11.16
  • Towpath and access closure dates:
  • 18.08.16 to 20.09.16 for the removal of existing access steps and closure of access, piling new waterway wall etc.
  • 10.10.16 to 17.11.16 for installing the new steps and surfacing to newly widened
  • The towpath will be re-opened for one day on 10th Sept for the pre-arranged Canal Canter event.
Advertisements

2 thoughts on “Better late than never

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s